Project Alibunar

Reconstruction, rationalization and maintenance of public lighting in inhabited places of Alibunar Municipality

  • Guaranteed annual savings 973.412,24 kWh or 69,53%
  • Total energy savings project 14.601.183,60 kWh
  • The project reduces CO2 emissions by 69,53% or a total of 16.046,70 tons of CO2
  • Implemented a total of 4.324 luminaires and 92 control systems for remote control
  • Technology – Thorn LED luminaires
  • Project’s Status – Project in the guarantee phase
  • Currently – savings being achieved in the project:

%

BETTER LIGHTING

  • Preparation phase 100% 100%
  • Implementation phase 100% 100%
  • Guaranteeing phase 2.55% 2.55%

%

Saving electricity

Impact of the project on environmental protection:
69,53% reduction CO2 emission or a total 16.046,70 tons of CO2

SMART ENERGY INVESTMENT

A reliable partner to Local-Self Governments in raising the level of public lighting services