Project Kovin

Reconstruction, rationalization and maintenance of public lighting in inhabited places of Kovin Municipality

  • Guaranteed annual savings 2.220.663,16​ kWh or 79%
  • Total energy savings project 33.309.947,34 kWh
  • The project reduces CO2 emissions by 79% or a total of 36.607,63 tons of CO2
  • Implemented a total of 4.982 luminaires and 126 control systems for remote control
  • Technology –Schreder LED luminaires
  • Project’s Status – Project in the guarantee phase
  • Currently – savings being achieved in the project:

%

BETTER LIGHTING

  • Preparation phase 100% 100%
  • Implementation phase 100% 100%
  • Guaranteeing phase 19.05% 19.05%

%

Saving electricity

Impact of the project on environmental protection:
79% reduction CO2 emission or a total 36.607,63 tons of CO2

SMART ENERGY INVESTMENT

A reliable partner to Local-Self Governments in raising the level of public lighting services